Division (Qualified opinion)X1
United Kingdom
Based on the examination referred to above, it is my opinion that, for the abovementioned period, the management and control systems established for the programme … (name of operational programme, CCI code number, period) complied with the applicable requirements of Articles 58 to 62 of Council Regulation (EC) No 1083/2006 and Section 3 of Commission Regulation (EC) No 1828/2006 and functioned effectively so as to provide reasonable assurance that statements of expenditure presented to the Commission are correct and, as a consequence, reasonable assurance that the underlying transactions are legal and regular, except in the following respects: … f1 .
My reasons for considering that this (these) aspect(s) of the systems did not comply with the requirements and/or did not operate in such a way as to give a reasonable assurance on the correctness of the statements of expenditure presented to the Commission are as follows … f2 .
I estimate the impact of the qualification(s) to be … of the total expenditure declared. The Community contribution affected is thus … .
Annotations
Editorial notes
Footnotes
- f1
-
Indicate the body or bodies and the aspect(s) of their systems that did not comply with requirements and/or did not operate effectively.
- f2
-
Indicate for each body and each aspect of the system the reasons for the qualification.