OpenLegislation

Article 132 Date of presentation of applications for interim payment and payment delays

United Kingdom

Original text. Later amendments are not shown.

1.

The certifying authority shall send requests for interim payments for each cross-border programme to the Commission, as far as possible, on three separate occasions a year. For a payment to be made by the Commission in the current year, the latest date on which a payment application shall be submitted is 31 October.

2.

Subject to available funding, and the absence of a suspension of payments in accordance with Article 136, the Commission shall make the interim payment no later than two months after the date on which a payment application meeting the above conditions referred to in Article 131 is registered with the Commission.