Division 1 The national regulatory authority shall require transmission system operators to partially or fully withdraw systematically underutilised contracted capacity on an interconnection point by a network user where that user has not sold or offered under reasonable conditions its unused capacity and where other network users request firm capacity. Contracted capacity is considered to be systematically underutilised in particular if:F1F2
United Kingdom
- (a)
the network user uses less than on average 80 % of its contracted capacity both from 1 April until 30 September and from 1 October until 31 March with an effective contract duration of more than one year for which no proper justification could be provided; or
- (b)
the network user systematically nominates close to 100 % of its contracted capacity and renominates downwards with a view to circumventing the rules laid down in point 2.2.3(3).
Annotations
Textual amendments
- F1
- F2
Words in Annex 1 point 2.2.5(1) substituted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), reg. 1(1), Sch. 2 para. 19(8)(a); 2020 c. 1, Sch. 5 para. 1(1)