Division 6.2 Evaluation of the action plan’s effectiveness shall in particular include the following actions:
United Kingdom
- (a)
verification of whether the action plan is correctly implemented and completed according to schedule;
- (b)
verification of whether the expected outcome is achieved;
- (c)
verification of whether in the meantime the initial conditions have changed and the risk control measures defined in the action plan are still appropriate for the given circumstances;
- (d)
verification of whether other risk control measures are necessary.