Division B.2 Determination of transferred CO2
United Kingdom
Each operator shall determine the amount of CO2 transferred from and to the capture installation in accordance with Article 49 by means of measurement methodologies carried out in accordance with Articles 40 to 46.
Only where the operator of the installation transferring CO2 to the capture installation demonstrates to the satisfaction of the competent authority that CO2 transferred to the capture installation is transferred in total and to at least equivalent accuracy, may the competent authority allow that operator to use a calculation-based methodology in accordance with Article 24 or 25 to determine the amount Tinput instead of a measurement-based methodology in accordance with Article 40 to 46 and Article 49.