  1. (1)

    The monitoring plan approved by the competent authority;

  2. (2)

    F1Documents justifying the selection of the monitoring methodology and the documents justifying temporal or non-temporal changes of monitoring methodologies and, where applicable, tiers approved by the competent authority;

  3. (3)

    All relevant updates of monitoring plans notified to the competent authority in accordance with Article 15, and the competent authority’s replies;

  4. (4)

    All written procedures referred to in the monitoring plan, including the sampling plan where relevant, the procedures for data flow activities and the procedures for control activities;

  5. (5)

    A list of all versions used of the monitoring plan and all related procedures;

  6. (6)

    Documentation of the responsibilities in connection to the monitoring and reporting;

  7. (7)

    The risk assessment performed by the operator or aircraft operator, where applicable;

  8. (8)

    The improvement reports in accordance with Article 69;

  9. (9)

    The verified annual emission report;

  10. (10)

    The verification report;

  11. (11)

    Any other information that is identified as required for the verification of the annual emissions report.

Annotations

Textual amendments

F1

Substituted by Commission Implementing Regulation (EU) 2018/2066 of 19 December 2018 on the monitoring and reporting of greenhouse gas emissions pursuant to Directive 2003/87/EC of the European Parliament and of the Council and amending Commission Regulation (EU) No 601/2012 (Text with EEA relevance).