# Commission Regulation (EU) No 965/2012 of 5 October 2012 laying down technical requirements and administrative procedures related to air operations pursuant to Regulation (EC) No 216/2008 of the European Parliament and of the Council, Division (d): When a finding is detected during oversight or by any other means, the CAA shall, without prejudice to any additional action required by Regulation (EC) No 216/2008 and its Implementing Rules, communicate the finding to the organisation in writing and request corrective action to address the non-compliance(s) identified. Where relevant, the CAA shall inform the State in which the aircraft is registered.

Extent: E+W+S+N.I.

(1)In the case of level 1 findings the CAA shall take immediate and appropriate action to prohibit or limit activities, and if appropriate, it shall take action to revoke the certificate , specialised operations authorisation or specific approval or to limit or suspend it in whole or in part, depending upon the extent of the level 1 finding, until successful corrective action has been taken by the organisation.
(2)In the case of level 2 findings, the CAA shall:
(i)grant the organisation a corrective action implementation period appropriate to the nature of the finding that in any case initially shall not be more than three months. At the end of this period, and subject to the nature of the finding, the CAA may extend the three-month period subject to a satisfactory corrective action plan agreed by the CAA; and
(ii)assess the corrective action and implementation plan proposed by the organisation and, if the assessment concludes that they are sufficient to address the non-compliance(s), accept these.
(3)Where an organisation fails to submit an acceptable corrective action plan, or to perform the corrective action within the time period accepted or extended by the CAA, the finding shall be raised to a level 1 finding and action taken as laid down in (d)(1).
(4) The CAA shall record all findings it has raised or that have been communicated to it in accordance with point (e) and, where applicable, the enforcement measures it has applied, as well as all corrective actions and the date of action closure for findings.

---
Source: https://www.legislation.gov.uk/eur/2012/965/annex/II/division/subpart+gen/division/section+iii/division/arogen350/division/d (the official version)