1.

The eligibility of expenditure shall be determined on the basis of national rules, except where specific rules are laid down in, or on the basis of, this Regulation or the Fund-specific rules.

2.

Expenditure shall be eligible for a contribution from F1support for rural development if it has been incurred by a beneficiary and paid between the date of submission of the programme to the Commission or from 1 January 2014, whichever is earlier, and 31 December 2023. In addition, expenditure shall only be eligible for F2support for rural development if the relevant aid is actually paid by the paying agency between 1 January 2014 and 31 December 2023.

F33.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4.

In the case of costs reimbursed pursuant to points (b) and (c) of the first subparagraph of Article 67(1), the actions constituting the basis for reimbursement shall be carried out between 1 January 2014 and 31 December 2023.

F45.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

6.

Operations shall not be selected for support by F5support for rural development where they have been physically completed or fully implemented before the application for funding under the programme is submitted by the beneficiary to the managing authority, irrespective of whether all related payments have been made by the beneficiary.

F67.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

8.

This paragraph shall apply to operations which generate net revenue during their implementation and to which paragraphs 1 to 6 of Article 61 do not apply.

The eligible expenditure of the operation F7receiving support for rural development shall be reduced by the net revenue not taken into account at the time of approval of the operation directly generated only during its implementation, not later than at the final payment claim submitted by the beneficiary. Where not all the costs are eligible for co-financing, the net revenue shall be allocated pro rata to the eligible and non-eligible parts of the cost.

This paragraph shall not apply to:

(a)

technical assistance;

(b)

financial instruments;

(c)

repayable assistance subject to an obligation for full repayment;

(d)

prizes;

F8(e)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(f)

operations for which public support takes the form of lump sums or standard scale unit costs provided that the net revenue has been taken into account ex ante;

(g)

operations implemented under a joint action plan provided that the net revenue has been taken into account ex ante;

F9(h)

operations for which amounts or rates of support are defined in Annex II to F10Regulation (EU) No 1305/2013 or in the EMFF Regulation with the exception of those operations for which reference is made to this paragraph in the EMFF Regulation; or

(i)

operations for which the total eligible cost does not exceed EUR 100 000.

For the purposes of this Article and Article 61, any payment received by the beneficiary arising from contractual penalties as a result of a breach of contract between the beneficiary and a third party or third parties or that has occurred as a result of the withdrawal of an offer by a third party chosen under public procurement rules (the 'deposit') shall not be considered as revenue and shall not be deducted from the eligible expenditure of the operation.

9.

Expenditure that becomes eligible as a result of an amendment to a programme shall only be eligible from the date of submission to the F11relevant authority of the request for amendment F12....

The Fund-specific rules for the EMFF may derogate from the first subparagraph.

10.

By way of derogation from paragraph 9, specific provisions on the starting date of eligibility may be established in F13Regulation (EU) No 1305/2013.

F14By way of derogation from paragraph 9, expenditure for operations for fostering crisis response capacities in the context of the COVID-19 outbreak shall be eligible as of 1 February 2020.

F1511.

An operation may receive support for rural development or from one or more programmes and from CMO support or direct payment support or support under other F16assimilated direct legislation, provided that the expenditure declared is not declared more than once.

Annotations

Textual amendments

F1

Words in Art. 65(2) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(b)(i) (as amended by S.I. 2020/1542, regs. 1(2), 13(9)(e)(ii)); 2020 c. 1, Sch. 5 para. 1(1)

F2

Words in Art. 65(2) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(b)(ii); 2020 c. 1, Sch. 5 para. 1(1)

F3

Art. 65(3) omitted (31.12.2020) by virtue of The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(c); 2020 c. 1, Sch. 5 para. 1(1)

F4

Art. 65(5) omitted (31.12.2020) by virtue of The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(c); 2020 c. 1, Sch. 5 para. 1(1)

F5

Words in Art. 65(6) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(ca) (as amended by S.I. 2020/1542, regs. 1(2), 13(9)(e)(iv)); 2020 c. 1, Sch. 5 para. 1(1)

F6

Art. 65(7) omitted (31.12.2020) by virtue of The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(cb) (as amended by S.I. 2020/1542, regs. 1(2), 13(9)(e)(iv)); 2020 c. 1, Sch. 5 para. 1(1)

F7

Words in Art. 65(8) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(d)(i) (as amended by S.I. 2020/1542, regs. 1(2), 13(9)(e)(v)(aa)); 2020 c. 1, Sch. 5 para. 1(1)

F8

Art. 65(8)(e) omitted (31.12.2020) by virtue of The State Aid (Revocations and Amendments) (EU Exit) Regulations 2020 (S.I. 2020/1470), reg. 1(2), Sch. 1 para. 7(7) (with Sch. 3)

F9

Substituted by Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council of 18 July 2018 on the financial rules applicable to the general budget of the Union, amending Regulations (EU) No 1296/2013, (EU) No 1301/2013, (EU) No 1303/2013, (EU) No 1304/2013, (EU) No 1309/2013, (EU) No 1316/2013, (EU) No 223/2014, (EU) No 283/2014, and Decision No 541/2014/EU and repealing Regulation (EU, Euratom) No 966/2012.

F10

Words in Art. 65(8)(h) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(d)(ii)(aa); 2020 c. 1, Sch. 5 para. 1(1)

F11

Words in Art. 65(9) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(e)(i); 2020 c. 1, Sch. 5 para. 1(1)

F12

Words in Art. 65(9) omitted (31.12.2020) by virtue of The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(e)(ii); 2020 c. 1, Sch. 5 para. 1(1)

F13

Words in Art. 65(10) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(f); 2020 c. 1, Sch. 5 para. 1(1)

F14

Inserted by Regulation (EU) 2020/460 of the European Parliament and of the Council of 30 March 2020 amending Regulations (EU) No 1301/2013, (EU) No 1303/2013 and (EU) No 508/2014 as regards specific measures to mobilise investments in the healthcare systems of Member States and in other sectors of their economies in response to the COVID-19 outbreak (Coronavirus Response Investment Initiative).

F15

Art. 65(11) substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 11(6)(g) (as amended by S.I. 2020/1542, regs. 1(2), 13(9)(e)(vii)); 2020 c. 1, Sch. 5 para. 1(1)

F16

Words in Art. 65(11) substituted (27.2.2025) by The Retained EU Law (Revocation and Reform) Act 2023 (Consequential Amendments) Regulations 2025 (S.I. 2025/82), reg. 1(2), Sch. 15 para. 102(2)(c)

Extent

E1

This version of this provision applies to England and Northern Ireland only; separate versions have been created for Scotland and Wales

Notes on the whole EU Regulation

Textual amendments

F1

Regulation revoked in so far as relating to the European Maritime and Fisheries Fund (31.12.2020) by The Common Fisheries Policy (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1542), reg. 1(3), Sch. Pt. 2

Notes on Part TWO

Textual amendments

F1

Pt. 2 heading substituted (31.12.2020) by The European Structural and Investment Funds Common Provisions (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/785), regs. 1, 5(1) (as amended by S.I. 2020/1542, regs. 1(2), 13(3)(a)); 2020 c. 1, Sch. 5 para. 1(1)