Annex
United Kingdom
Publication of the information referred to in Article 11(2)
| Capacity allocation period | Forecasted cross zonal capacity to be published | Offered capacity to be published |
|---|---|---|
| Yearly | One week before the yearly allocation process but no later than 15 December, for all months of the following year | One week before the yearly allocation process but no later than 15 December |
| Monthly | Two working days before the monthly allocation process for all days of the following month | Two working days before the monthly allocation process |
| Weekly | Each Friday, for all days of the following week | One day before the weekly allocation process |
| Day-ahead | One hour before spot market gate closure, for each market time unit | |
| Intra-day | One hour before the first intra-day allocation and then real-time, for each market time unit |