Publication of the information referred to in Article 11(2)

Capacity allocation periodForecasted cross zonal capacity to be publishedOffered capacity to be published
YearlyOne week before the yearly allocation process but no later than 15 December, for all months of the following yearOne week before the yearly allocation process but no later than 15 December
MonthlyTwo working days before the monthly allocation process for all days of the following monthTwo working days before the monthly allocation process
WeeklyEach Friday, for all days of the following weekOne day before the weekly allocation process
Day-aheadOne hour before spot market gate closure, for each market time unit
Intra-dayOne hour before the first intra-day allocation and then real-time, for each market time unit