Article 14 Forecast generation
United Kingdom
For their control areas, TSOs shall calculate and F1publish the following information F2...:
the sum of generation capacity (MW) installed for all existing production units equalling to or exceeding 1 MW installed generation capacity, per production type;
information about production units (existing and planned) with an installed generation capacity equalling to or exceeding 100 MW. The information shall contain:
the unit name,
the installed generation capacity (MW),
the location,
the voltage connection level,
the bidding zone,
the production type;
an estimate of the total scheduled generation (MW) per bidding zone, per each market time unit of the following day;
a forecast of wind and solar power generation (MW) per bidding zone, per each market time unit of the following day.
The information laid down:
in point (a) of paragraph 1 shall be published annually no later than one week before the end of the year;
in point (b) of paragraph 1 shall be published annually for the three following years no later than one week before the beginning of the first year to which the data relates;
in point (c) of paragraph 1 shall be published no later than F35 p.m., one day before actual delivery takes place;
Production units located in a TSO’s control area shall provide that TSO with all the relevant information required to calculate the data laid down in paragraph 1.
Production units shall be considered as primary owners of the relevant information they provide.
Annotations
Textual amendments
- F1
Word in Art. 14(1) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(2)(a); 2020 c. 1, Sch. 5 para. 1(1)
- F2
Words in Art. 14(1) omitted (31.12.2020) by virtue of The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(2)(b); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Words in Art. 14(2)(c) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(3)(a); 2020 c. 1, Sch. 5 para. 1(1)
- F4
Words in Art. 14(2)(d) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(3)(b)(i); 2020 c. 1, Sch. 5 para. 1(1)
- F5
Words in Art. 14(2)(d) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(3)(b)(ii); 2020 c. 1, Sch. 5 para. 1(1)
- F6
Words in Art. 14(2)(d) omitted (31.12.2020) by virtue of The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 13(3)(b)(iii); 2020 c. 1, Sch. 5 para. 1(1)