# Commission Regulation (EU) No 312/2014 of 26 March 2014 establishing a Network Code on Gas Balancing of Transmission Networks (Text with EEA relevance), Article 15: Re-nomination procedure at interconnection points

Extent: E+W+S+N.I.

1. A network user shall be entitled to submit re-nominations within the re-nomination period which starts immediately after the confirmation deadline and ends no earlier than three hours before the end of gas day D. The transmission system operator shall start a re-nomination cycle at the start of every hour within the re-nomination period.
2. The last re-nomination received by the transmission system operator from a network user before the re-nomination cycle starts shall be taken into account by the transmission system operator in the re-nomination cycle.
3. The transmission system operator shall send the message regarding the confirmed quantities to the respective network users within two hours from the start of each re-nomination cycle. The start time of the effective gas flow change shall be two hours from the start of the re-nomination cycle, unless:
(a) a later time is requested by the network user; or
(b) an earlier time is allowed by the transmission system operator.
4. It shall be assumed that any change to the gas flow occurs at the start of each hour.

---
Source: https://www.legislation.gov.uk/eur/2014/312/article/15 (the official version)
Page: https://openlegislation.uk/eu-regulation-2014-312/article-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.