Article 48 Discontinuation of cross-border cooperation programmes
United Kingdom
Where none of the participating IPA II beneficiaries has concluded the financing agreement by the end of the year following the year of the adoption of the programme, the Commission shall discontinue the cross-border cooperation programme.
European Regional Development Fund annual instalments already committed shall remain available for their normal lifetime but may be used only for activities which take place exclusively in the Member States concerned and contracted before the Commission discontinuation decision. The managing authority shall transmit the final report within three months of the closure of the contracts to the Commission which shall proceed in conformity with paragraphs 2 and 3.
Where the cross-border cooperation programme cannot be implemented owing to problems arising in relations between participating countries and in other duly justified cases, the Commission may decide to discontinue the programme before the expiry date of the period of execution, at the request of the JMC or on its own initiative after having consulted the JMC.
Where the programme is discontinued, the managing authority shall transmit the final report within six months following the Commission's decision. After clearing the previous pre-financing payments, the Commission shall pay the final balance or, where appropriate, issue the recovery order. The Commission shall also decommit the balance of commitments.
As an alternative, it may be decided to reduce the programme's allocation to the programme scope in accordance with Article 31(5).
In the cases referred to in paragraphs 1 and 2, non-committed support from European Regional Development Fund corresponding to annual instalments not yet committed or annual instalments committed and decommitted totally or partially during the same budgetary year, which have not been re-allocated to another programme of the same category of external cooperation programmes shall be allocated to the internal cross-border cooperation programmes in accordance with Article 4 of Regulation (EU) No 1299/2013.
IPA II assistance corresponding to annual instalments not yet committed or annual instalments committed and decommitted totally or partially during the same budgetary year shall be used to finance other programmes or projects eligible for IPA II assistance.