Article 4 Force majeure and exceptional circumstances
United Kingdom
F1As regards direct payments, if a beneficiary has been unable to comply with the eligibility criteria or other obligations as a result of force majeure or exceptional circumstances he shall retain his right to aid in respect of the area or animals eligible at the time when the case of force majeure or the exceptional circumstance occurred.
As regards rural development support measures under Articles 28, 29, 33 and 34 of Regulation (EU) No 1305/2013, if a beneficiary has been unable to fulfil the commitment as a result of force majeure or exceptional circumstances, the respective payment shall be proportionally withdrawn for the years during which the case of force majeure or exceptional circumstances occurred. The withdrawal shall concern only those parts of the commitment for which additional costs or income foregone did not take place before the force majeure or exceptional circumstances occurred. No withdrawal shall apply in relation to the eligibility criteria and other obligations and no administrative penalty shall apply.
As regards other rural development support measures, F2the relevant authority shall not require the partial or full reimbursement of the support in case of force majeure or exceptional circumstances. In case of multiannual commitments or payments, reimbursement of the support received in previous years shall not be required and the commitment or payment shall be continued in the subsequent years in accordance with its original duration.
F3When the non-compliance resulting from such force majeure or exceptional circumstances concerns cross-compliance, the corresponding administrative penalty as referred to in Article 91(1) of Regulation (EU) No 1306/2013 shall not be applied.
Cases of force majeure and exceptional circumstances shall be notified in writing to the competent authority, with relevant evidence to the satisfaction of the competent authority, within F4fifteen working dayseight weeks from the date on which the beneficiary or the person entitled through him, is in a position to do so.
Annotations
Textual amendments
- F1
Words in Art. 4(1) omitted (31.12.2020 for the purposes of common organisation of the markets and rural development measures) by virtue of The Common Agricultural Policy (Financing, Management and Monitoring Supplementary Provisions) (Miscellaneous Amendments) (EU Exit) Regulations 2019 (S.I. 2019/765), regs. 1, 6(4)(a) (as substituted by S.I. 2020/1445, regs. 1(2)(b), 9(5)); 2020 c. 1, Sch. 5 para. 1(1); and omitted (E.) (1.1.2024) by virtue of The Agriculture (Delinked Payments and Consequential Provisions) (England) Regulations 2023 (S.I. 2023/1430), reg. 1(2)(a), Sch. 4 para. 4(4)
- F2
Words in Art. 4(1) substituted (31.12.2020 for the purposes of common organisation of the markets and rural development measures) by The Common Agricultural Policy (Financing, Management and Monitoring Supplementary Provisions) (Miscellaneous Amendments) (EU Exit) Regulations 2019 (S.I. 2019/765), regs. 1, 6(4)(b) (as substituted by S.I. 2020/1445, regs. 1(2)(b), 9(5)); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Words in Art. 4(1) revoked (E.) (1.1.2024) by The Agriculture (Removal of Cross-Compliance and Miscellaneous Revocations and Amendments, etc.) (England) Regulations 2023 (S.I. 2023/816), reg., Sch. Pt. 1 para. 1 Table 2 (with Sch. Pt. 2 para. 2)
- F4
Words in Art. 4(2) substituted in so far as it relates to direct payments (E.) (1.1.2021) by The Direct Payments to Farmers and Cross-Compliance (Simplifications) (England) (Amendment) Regulations 2020 (S.I. 2020/1387), regs. 1(1), 7(3) (with reg. 1(2)); and substituted in so far as it relates to rural development support measures (E.) (28.7.2022) by The Rural Development (Amendment) (England) Regulations 2022 (S.I. 2022/765), regs. 1(1), 9(2)