Article 43 Content of projects
United Kingdom
Project application documents shall contain at least:
an analysis of the problems and needs justifying the project, taking into account the programme strategy and its expected contribution to address the corresponding priority;
an assessment of its cross-border impact;
the logical framework;
an assessment of the sustainability of the project's expected results after project's completion;
objectively verifiable indicators;
information on the geographic coverage and target groups of the project;
the expected project implementation period and detailed work plan;
an analysis of the effects of the project on the cross-cutting issues referred to in point 3(d) of Article 4 where relevant;
the project implementation requirements, including the following:
- (i)
identification of the beneficiaries and designation of the lead beneficiary, providing guarantees of its competence in the domain concerned as well as its administrative and financial management capacity;
- (ii)
description of the project management and implementation structure;
- (iii)
arrangements among beneficiaries in line with Article 46;
- (iv)
monitoring and evaluation arrangements;
- (v)
information and communication plans, in particular, measures to acknowledge the Union support to the project;
detailed financial plan and budget.
Project applications for projects including an infrastructure component of at least EUR 1 million shall in addition contain:
a detailed description of the infrastructure investment and its location;
a detailed description of the capacity building component of the project, except in duly justified cases;
a full feasibility study or equivalent carried out, including the options analysis, the results, and independent quality review;
an assessment of its environmental impact in compliance with the Directive 2011/92/EU of the European Parliament and of the Councilf1 and, for the participating countries which are parties to it, UN/ECE Espoo Convention on Environmental Impact Assessment in a Transboundary Context of 25 February 1991;
evidence of ownership by the beneficiaries or access to the land;
building permit.
Exceptionally and in duly justified cases, the Managing Authority may accept a later submission of the documents referred to in point (f).
Annotations
Footnotes
- f1
-
Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment (OJ L 26, 28.1.2012, p. 1).