Article 17 Control requirements

United Kingdom

Original text. Later amendments are not shown.

1.

The relevant TSO and the transmission-connected demand facility owner or the transmission-connected distribution system operator shall agree on the schemes and settings of the different control devices of the transmission-connected demand facility or the transmission-connected distribution system relevant for system security.

2.

The agreement shall cover at least the following elements:

(a)

isolated (network) operation;

(b)

damping of oscillations;

(c)

disturbances to the transmission network;

(d)

automatic switching to emergency supply and restoration to normal topology;

(e)

automatic circuit-breaker re-closure (on 1-phase faults).

3.

The relevant TSO and the transmission-connected demand facility owner or the transmission-connected distribution system operator shall agree on any changes to the schemes and settings of the different control devices of the transmission-connected demand facility or the transmission-connected distribution system relevant for system security.

4.

With regard to priority ranking of protection and control, the transmission-connected demand facility owner or the transmission-connected distribution system operator shall set the protection and control devices of its transmission-connected demand facility or its transmission-connected distribution system respectively, in compliance with the following priority ranking, organised in decreasing order of importance:

(a)

transmission network protection;

(b)

transmission-connected demand facility or transmission-connected distribution system protection;

(c)

frequency control (active power adjustment);

(d)

power restriction.