# Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Code on Demand Connection (Text with EEA relevance), Article 50: Power to grant derogations

Extent: E+W+S+N.I.

1. The regulatory authority may, at the request of a demand facility owner or prospective owner, and a DSO/CDSO or prospective operator, relevant system operator or relevant TSO, grant demand facility owners or prospective owners, and DSOs/CDSOs or prospective operators, relevant system operators or relevant TSOs derogations from one or more provisions of this Regulation for new and existing transmission-connected demand facilities, transmission-connected distribution facilities, distribution systems and demand units in accordance with Articles 51 to 53.
2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

---
Source: https://www.legislation.gov.uk/eur/2016/1388/article/50 (the official version)
Page: https://openlegislation.uk/eu-regulation-2016-1388/article-50
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.