# Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (Text with EEA relevance), Article 41: Control requirements

Extent: E+W+S+N.I.

1. During the synchronisation of a DC-connected power park module to the AC collection network, the DC-connected power park module shall have the capability to limit any voltage changes to a steady-state level specified by the relevant system operator, in coordination with the relevant TSO. The level specified shall not exceed 5 per cent of the pre-synchronisation voltage. The relevant system operator, in coordination with the relevant TSO, shall specify the maximum magnitude, duration and measurement window of the voltage transients.
2. The DC-connected power park module owner shall provide output signals as specified by the relevant system operator, in coordination with the relevant TSO.

---
Source: https://www.legislation.gov.uk/eur/2016/1447/article/41 (the official version)
Page: https://openlegislation.uk/eu-regulation-2016-1447/article-41
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.