# Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance), Article 33: Procedure for type D power-generating modules

Extent: E+W+S+N.I.

The operational notification procedure for connection of each new type D power-generating module shall comprise:
(a) energisation operational notification (‘EON’);
(b) interim operational notification (‘ION’); and
(c) final operational notification (‘FON’).

---
Source: https://www.legislation.gov.uk/eur/2016/631/article/33 (the official version)
Page: https://openlegislation.uk/eu-regulation-2016-631/article-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.