# Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance), Article 8: Multiple TSOs

Extent: E+W+S+N.I.

1. Subject to paragraph 2, this Regulation applies to all TSOs in Great Britain.
2. The regulatory authority may assign the responsibility of a TSO to comply with one or some or all obligations under this Regulation to one or more specific TSOs by giving a direction in writing to each of the affected TSOs.

---
Source: https://www.legislation.gov.uk/eur/2016/631/article/8 (the official version)
Page: https://openlegislation.uk/eu-regulation-2016-631/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.