# Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance), Article 140: Process activation structure

Extent: E+W+S+N.I.

1. The process activation structure shall include:
(a) a FCP pursuant to Article 142;
(b) a FRP pursuant to Article 143 ...
(c) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2. The process activation structure may include:
(a) a RRP pursuant to Article 144;
(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(c) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(e) ... a time control process pursuant to Article 181.

---
Source: https://www.legislation.gov.uk/eur/2017/1485/article/140 (the official version)