# Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance), Article 184: Information on operational agreements

Extent: E+W+S+N.I.

1. Each TSO shall share the contents of its synchronous area operational agreement with the regulatory authority no later than 1 month before its entry into force.
2. All TSOs in the GB synchronous area shall publish the contents of their synchronous area operational agreement ... no later than 1 week after its entry into force.
3. Each TSO of each LFC block shall share the contents of its LFC block operational agreement with the regulatory authority.

---
Source: https://www.legislation.gov.uk/eur/2017/1485/article/184 (the official version)
Page: https://openlegislation.uk/eu-regulation-2017-1485/article-184
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.