1. All TSOs of the GB synchronous area shall publish the following information ... at least 3 months before the application of the synchronous area operational agreement:
(a) information on the process activation structure of the synchronous area, including at least information on the monitoring areas, LFC areas and LFC blocks defined and their respective TSOs; and
(b) information on the process responsibility structure of the synchronous area, including at least information on the processes developed in accordance with Article 140(1) and (2).
2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

---
Source: https://www.legislation.gov.uk/eur/2017/1485/article/186 (the official version)
Page: https://openlegislation.uk/eu-regulation-2017-1485/article-186
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.