# Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance), Article 49: Scheduled data exchange

Extent: E+W+S+N.I.

Unless otherwise provided by the TSO, each power generating facility owner of a power generating module which is a SGU in accordance with Article 2(1)(a) and 2(1)(e) connected to the distribution system shall provide the TSO and the DSO to which it has the connection point, with at least the following data:
(a)its scheduled unavailability, scheduled active power restriction and its forecasted scheduled active power output at the connection point;
(b)any forecasted restriction in the reactive power control capability ...
(c)...

---