  "url": "https://openlegislation.uk/eu-regulation-2017-1485/article-52",
  "json_url": "https://openlegislation.uk/eu-regulation-2017-1485/article-52.json",
  "legislation": "eur/2017/1485",
  "legislation_title": "Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance)",
  "legislation_url": "https://openlegislation.uk/eu-regulation-2017-1485",
  "path": "article/52",
  "kind": "article",
  "number": "52",
  "heading": "Data exchange between TSOs and transmission-connected demand facilities",
  "text": "1. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO:\n(a) electrical data of the transformers connected to the transmission system;\n(b) characteristics of the load of the demand facility; and\n(c) characteristics of the reactive power control.\n2. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO:\n(a) scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast;\n(b) any forecasted restriction in the reactive power control capability;\n(c) in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed ...\n(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .\n3. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time:\n(a) active and reactive power at the connection point; and\n(b) the minimum and maximum power range to be curtailed.\n4. Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.",
  "extent": "E+W+S+N.I.",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Art. 52(2)(d) and word omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 43 (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/eur/2017/1485/article/52",
    "retrieved_at": "2026-11-01T14:44:42.168103+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}