F1The regulatory authority must within six months of receipt of the joint proposal, pursuant to Article 5(6) and (7), after consulting the project promoters concerned, endeavour to take a coordinated decision with the national regulatory authorities of the member States concerned on the cross-border allocation of investment costs to be borne by each transmission system operator of the project. Where the regulatory authority and the national regulatory authorities concerned have not reached an agreement within that deadline, the regulatory authority must inform the Secretary of State without delay.

Annotations

Textual amendments

F1

Annex 3 point 4 substituted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 1 para. 20(5); 2020 c. 1, Sch. 5 para. 1(1)