Article 48 Balancing energy for reserve replacement process
United Kingdom
1.
Each connecting TSO shall calculate and settle the activated volume of balancing energy for the reserve replacement process with balancing service providers pursuant to paragraphs 1 and 2 of Article 45.
2.
The price, be it positive, zero or negative, of the activated volume of balancing energy for reserve replacement process shall be defined for each direction F1... as defined in the Table 1.
Annotations
Textual amendments
- F1
Words in Art. 48(2) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 30; 2020 c. 1, Sch. 5 para. 1(1)