Article 61 Cost-benefit analysis

United Kingdom

Original text. Later amendments are not shown.

1.

When TSOs are required to carry out a cost-benefit analysis pursuant to this Regulation, they shall establish the criteria and methodology for the cost-benefit analysis and submit them to the F1regulatory authority by six months before the start of the cost-benefit analysis. The F2... regulatory authorities shall be entitled to F3... require amendments to the criteria and methodology.

2.

The cost-benefit analysis shall at least take into account:

(a)

the technical feasibility;

(b)

the economic efficiency;

(c)

the impact on competition and integration of balancing markets;

(d)

the costs and benefits of implementation;

(e)

the impact on F4... balancing costs;

(f)

the potential impact on F5... electricity market prices;

(g)

the ability of TSOs and balancing responsible parties to fulfil their obligations;

(h)

the impact on market parties in terms of additional technical or IT requirements assessed in cooperation with the affected stakeholders.

3.

All concerned TSOs shall provide the results of the cost-benefit analysis to F6the regulatory authority, together with a justified proposal on how to address possible issues identified by the cost-benefit analysis.

Annotations

Textual amendments

F1

Words in Art. 61(1) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(2)(a); 2020 c. 1, Sch. 5 para. 1(1)

F2

Word in Art. 61(1) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(2)(b)(i); 2020 c. 1, Sch. 5 para. 1(1)

F3

Word in Art. 61(1) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(2)(b)(ii); 2020 c. 1, Sch. 5 para. 1(1)

F4

Words in Art. 61(2)(e) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(3)(a); 2020 c. 1, Sch. 5 para. 1(1)

F5

Word in Art. 61(2)(f) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(3)(b); 2020 c. 1, Sch. 5 para. 1(1)

F6

Words in Art. 61(3) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 39(4); 2020 c. 1, Sch. 5 para. 1(1)