# Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration (Text with EEA relevance), Article 26: Re-energisation procedure

Extent: E+W+S+N.I.

1. The re-energisation procedure of the restoration plan shall contain a set of measures allowing the TSO to apply:
(a) a top-down re-energisation strategy; and
(b) a bottom-up re-energisation strategy.
2. Regarding the bottom-up re-energisation strategy, the re-energisation procedure shall contain at least measures for:
(a) managing voltage and frequency deviations due to re-energisation;
(b) monitoring and managing island operation; and
(c) resynchronising island operation areas.

---