# Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration (Text with EEA relevance), Article 32: Resynchronisation procedure

Extent: E+W+S+N.I.

The resynchronisation procedure of the restoration plan shall include, at least:
(a) the appointment of a resynchronisation leader;
(b) the measures allowing the TSO to apply a resynchronisation strategy; and
(c) the maximum limits for phase angle, frequency and voltage differences for connecting lines.

---