1. Each restoration service provider which is a power generating module delivering black start service shall execute a black start capability test, at least every three years, following the methodology laid down in Article 45(5) of Regulation (EU) 2016/631.
2. Each restoration service provider which is a power generating module delivering a quick re-synchronisation service shall execute tripping to houseload test after any changes of equipment having an impact on its houseload operation capability, or after two unsuccessful consecutive tripping in real operation, following the methodology laid down in Article 45(6) of Regulation (EU) 2016/631.

---
Source: https://www.legislation.gov.uk/eur/2017/2196/article/44 (the official version)
Page: https://openlegislation.uk/eu-regulation-2017-2196/article-44
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.