# Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 (Text with EEA relevance), Article 34: Coordination of interruption process

Extent: E+W+S+N.I.

The transmission system operator that initiates the interruption shall notify the relevant adjacent TSO. ... Transmission system operators shall notify their respective affected network users as soon as possible, but with due regard to the reliability of the information.

---
Source: https://www.legislation.gov.uk/eur/2017/459/article/34 (the official version)
Page: https://openlegislation.uk/eu-regulation-2017-459/article-34
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.