Article 25 Conditions for offering payable price approaches
United Kingdom
Where and to the extent that the transmission system operator functions under a non-price cap regime, the conditions for offering payable price approaches shall be as follows:
for cases where only existing capacity is offered:
- (i)
the floating payable price approach shall be offered;
- (ii)
the fixed payable price approach shall not be allowed.
for incremental capacity and existing capacity offered in the same auction or same alternative allocation mechanism:
- (i)
the floating payable price approach may be offered;
- (ii)
the fixed payable price approach may be offered where one of the following conditions is met:
- (1)
an alternative allocation mechanism set out in Article 30 of Regulation (EU) 2017/459 is used;
- (2)
- (1)
Where and to the extent that the transmission system operator functions under a price cap regime, the floating payable price approach or the fixed payable price approach, or both, may be offered.
Annotations
Textual amendments
- F1
Words in Art. 25(1)(b)(ii)(2) inserted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 5 para. 7 (as amended by S.I. 2020/1016, regs. 1(2), 4(5)); 2020 c. 1, Sch. 5 para. 1(1)
Footnotes
- f1
-
Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC and amending Regulations (EC) No 713/2009, (EC) No 714/2009 and (EC) No 715/2009 (OJ L 115, 25.4.2013, p. 39).