The following additional requirements shall be fulfilled when applying combined data sampling:

  1. (a)

    the different operating sequences shall be obtained using the same non-road mobile machinery and engine;

  2. (b)

    the combined data sampling shall contain a maximum of three operating sequences;

  3. (c)

    each operating sequence in the combined data sampling shall contain a minimum of one Non-Road Transient Cycle (NRTC) work;

  4. (d)

    the operating sequences in the combined data sampling shall be obtained and put together in a chronological order;

  5. (e)

    the data analysis shall be applied to the complete combined data sampling;

  6. (f)

    the maximum period elapsed between the first and last operating sequence shall be 72 hours;

  7. (g)

    combined data sampling shall not be used if an engine malfunction occurs, as set out in point 8 of Appendix 2.