When planning, developing, implementing and reviewing its operational processes, the organisation shall ensure that during operation:

  1. (a)

    risk acceptance criteria and safety measures are applied (see 3.1.1. Risk assessment);

  2. (b)

    plan(s) to achieve the safety objectives are delivered (see 3.2. Safety objectives and planning);

  3. (c)

    information is collected to measure the correct application and effectiveness of the operational arrangements (see 6.1. Monitoring).