Article 3 Article 2 (interpretation)I1
England, Wales and Scotland
In article 2 (interpretation)—
in paragraph (1)—
for the definition of “MCS”, substitute—
in the appropriate places insert the following definitions—
““commissioning date”, in relation to an installation, means the date on which the installation is commissioned;”;
““MCS-certified installation” has the meaning set out in Schedule A1 to this Order;”;
““pause period” has the meaning given in article 8A;”;
““tariff period” means one of the following periods—
- (a)
the period beginning on 8th February 2016 and ending on 31st March 2016;
- (b)
the period of 3 months beginning on 1st April 2016; or
- (c)
any subsequent period of 3 months beginning on 1st July, 1st October, 1st January or 1st April;”;
in paragraph (2), omit “MCS-certified installation”; and
after paragraph (3), insert—
“(4)In this Order, a reference to a particular description of eligible installations is a reference to eligible installations of one of the descriptions in the first column of the table in Schedule 1A.”.
Annotations
Commencement
- I1
Art. 3 in force at 15.1.2016, see art. 1
Footnotes
- f1
-
European standards are published by the European Committee on Standardization (CEN): www.cen.eu.
- f2
-
ISO standards can be obtained from the International Organization for Standardization: www.iso.org.