OpenLegislation

Schedule

Original text. Later amendments are not shown.

“SCHEDULE 2

FIT applications data

Article 35A

1.

Within the first 5 working days of each tariff period, the Authority must determine and publish the data set out in paragraph 2.

2.

The data referred to in paragraph 1 are—

(a)

the aggregate total installed capacities of anaerobic digestion installations applied for within the deployment period;

(b)

the aggregate total installed capacities of hydro generating stations with total installed capacity of 100 kilowatts or less, applied for within the deployment period;

(c)

the aggregate total installed capacity of hydro generating stations with total installed capacity greater than 100 kilowatts applied for within the deployment period;

(d)

the aggregate total installed capacities of solar photovoltaic (other than stand-alone), with total installed capacity of 10 kilowatts or less, which were registered on the MCS database within the deployment period;

(e)

the aggregate total installed capacities of solar photovoltaic (other than stand-alone), with total installed capacity greater than 10 kilowatts but not exceeding 50 kilowatts, which were registered on the MCS database within the deployment period;

(f)

the aggregate total installed capacities of solar photovoltaic installations (other than stand-alone), with total installed capacity greater than 50 kilowatts applied for within the deployment period;

(g)

the aggregate total installed capacities of stand-alone solar photovoltaic installations applied for within the deployment period, including those which were registered on the MCS database within the deployment period;

(h)

the aggregate total installed capacities of wind installations, with total installed capacity of 50 kilowatts or less, which were registered on the MCS database within the deployment period;

(i)

the aggregate total installed capacities of wind installations, with total installed capacity greater than 50 kilowatts but not exceeding 100 kilowatts applied for within the deployment period;

(j)

the aggregate total installed capacities of wind installations, with total installed capacity greater than 100 kilowatts but not exceeding 1500 kilowatts, applied for within the deployment period; and

(k)

the aggregate total installed capacity of wind installations, with total installed capacity greater than 1500 kilowatts, applied for within the deployment period.

3.

In this Schedule—

  • “applied for” refers to an application for accreditation or preliminary accreditation made in respect of a relevant installation;

  • “the deployment period” in relation to a tariff period in which data is required to be determined and published, means the period of three months immediately preceding that tariff period;

  • “MCS database” means the database maintained by the Microgeneration Certification Scheme that records the details of MCS-certified installations; and

  • “relevant installation” has the meaning given in article 8B(4)(b).”