(1) Paragraph (2) applies where—
(a) the Authority receives notice that an installation which uses an eligible low-carbon energy source (“the existing installation”) has been extended; and
(b) either—
(i) a request for accreditation of the existing installation as an accredited FIT installation has been refused; or
(ii) if a request were made for accreditation of the existing installation, the request would be refused; and
(c) the commissioning date of the extension is before 15th January 2016.
(2) Where this paragraph applies, the Authority must—
(a) treat the extension as a separate eligible installation;
(b) decide whether or not to accredit the extension in accordance with Part 3; and
(c) where it decides to accredit the extension, assign the extension a tariff code based on the aggregate total installed capacity of both the extension and the existing installation.

---
Source: https://www.legislation.gov.uk/uksi/2012/2782/article/19 (the official version)
Page: https://openlegislation.uk/feed-in-tariffs-order-2012/article-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.