Article 4 Power to construct works
Subject to the provisions of this Order, the Company may within in the lines and situations and upon the lands delineated on the deposited plans and within the limits of deviation shown thereon and according to the levels shown on the deposited sections, construct and maintain the work hereinafter described, with all necessary works and conveniences connected therewith—
-
A quay, including berths for vessels and a container storage and handling park, enclosing an area of 7.27 hectares extending into the estuary of the river from the north-east bank of the estuary and being an extension in a north-westerly direction of the work as so described and authorised by the 1988 Act to the extent constructed, commencing at the north-western limit of that work as constructed and shown on the deposited plans and described thereon as “Limit of deviation and line of commencement of work” and terminating on a line shown on the deposited plans and described thereon as “Line of termination of work” between reference point TM2557834830, TM2564334930, TM2566434916 and TM2576135045.
Subject to the provisions of this Order, the Company may, within the limits of deviation, reconstruct, extend, enlarge, replace or relay the work and may maintain the same as reconstructed, extended, enlarged, replaced or relaid.
The Company may, by means of the work authorised by subsection (1) above, enclose and reclaim so much of the bed of the sea and of the river and of the foreshore adjacent to the dock as lies within the limits of deviation and may hold and use the same as part of the undertaking.
The work shall for all purposes form part of the undertaking of the Company as from time to time existing.