(1)

Not less than 56 days before commencing the construction of any tidal work the Company shall supply to the Authority plans of that work.

(2)

The Authority may appove plans submitted to it in accordance with this Schedule or may disapprove them or approve them conditionally and, if the Authority does not within 56 days of the submission to it of any plans notify the Company in writing of its approval of those plans (conditionally or unconditionally), or its disapproval of those plans, the Authority shall be deemed to have approved the plans.

(3)

The works shall not be constructed except in accordance with such plans as may have been approved (conditionally or unconditionally) by the Authority under this Schedule or deemed to have been approved in accordance with paragraph (2) or, in the event of the disapproval or a conditional approval of plans which is unacceptable to the Company, settled as provided in paragraph 4 below.