Article 28 Modification of Part 1 of the Compulsory Purchase Act 1965
Part 1 (compulsory acquisition under the Acquisition of Land Act 1981) of the 1965 Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.
In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order)” substitute “section 118 (legal challenges relating to applications for orders granting development consent) of the 2008 Act”.
In section 11A (powers of entry: further notice of entry)—
in subsection (1)(a), after “land” insert “under that provision”; and
in subsection (2), after “land” insert “under that provision”.
In section 22(2) (interests omitted from purchase), for “section 4 of this Act” substitute “article 22 (time limit for exercise of authority to acquire land compulsorily) of the Fenwick Solar Farm Order 2026”.
In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—
for paragraphs 1(2) and 14(2) substitute—
“(2)But see article 26(3) (acquisition of subsoil only) of the Fenwick Solar Farm Order 2026, which excludes the acquisition of subsoil only from this Schedule.”; and
after paragraph 29 insert—
“PART 4
INTERPRETATION
30.In this Schedule, references to entering on and taking possession of land do not include doing so under article 19 (protective works to buildings), article 30 (temporary use of land for constructing the authorised development) or article 31 (temporary use of land for maintaining the authorised development) of the Fenwick Solar Farm Order 2026.”.