# The Fenwick Solar Farm Order 2026, Part 3: OTHER DOCUMENTS TO BE CERTIFIED


(1)
Document name
(2)
Document reference
(3)
Revision number
(4)
Date
(5)
Examination Library Reference
Land Plan
EN010152/APP/2.1
0
31 October 2024
APP-006
Works Plan
EN010152/APP/2.2
1
12 December 2024
APP-214
Streets, Rights of Way and Access Plan
EN010152/APP/2.3
4
2 July 2025
REP3-004 and REP3-005
Traffic Regulation Measures Plan
EN010152/APP/2.4
0
31 October 2024
APP-009
Book of Reference
EN010152/APP/4.3
2
30 April 2025
REP1-009
Outline Design Parameters Statement
EN010152/APP/7.4
1
28 May 2025
REP2-027
Framework Construction Environmental Management Plan
EN010152/APP/7.7
3
2 July 2025
REP3-013
Framework Operational Environmental Management Plan
EN010152/APP/7.8
3
21 August 2025
REP5-007
Framework Decommissioning Environmental Management Plan
EN010152/APP/7.9
3
23 July 2025
REP4-019
Framework Soil Management Plan
EN010152/APP/7.10
2
23 July 2025
REP4-021
Framework Public Rights of Way Management Plan
EN010152/APP/7.13
4
21 August 2025
REP5-009
Framework Landscape and Ecological Management Plan
EN010152/APP/7.14
3
2 July 2025
REP3-017
Framework skills, supply chain and employment plan
EN010152/APP/7.15
0
31 October 2024
APP-204
Framework Battery Safety Management Plan
EN010152/APP/7.16
0
31 October 2024
APP-205
Framework Construction Traffic Management Plan
EN010152/APP/7.17
2
23 July 2025
REP4-027
Framework Site Waste Management Plan
EN010152/APP/7.18
0
31 October 2024
APP-208
Framework Archaeological Mitigation Strategy
EN010152/APP/8.16
1
28 May 2025
REP2-054

---
Source: https://www.legislation.gov.uk/uksi/2026/151/schedule/12/part/3 (the official version)
Page: https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-12/part-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.