# The Fenwick Solar Farm Order 2026, Paragraph 25


If by reason of the construction of the specified work the drainage authority’s access to land drainage infrastructure, flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the drainage authority to maintain the land drainage infrastructure, flood defence or use the equipment no less effectively than was possible before the obstruction within 24 hours of or as soon as reasonably practicable after the undertaker becoming aware of such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2026/151/schedule/14/paragraph/25 (the official version)
Page: https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-14/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.