# The Fenwick Solar Farm Order 2026, Paragraph 82: National Grid Connection Works


The undertaker must not carry out the National Grid Connection Works, or any part of it except with the approval of National Grid Electricity Transmission Plc in accordance with paragraph 91.

---
Source: https://www.legislation.gov.uk/uksi/2026/151/schedule/14/paragraph/82 (the official version)
Page: https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-14/paragraph-82
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.