Paragraph 84 National Grid Connection Works

Original text. Later amendments are not shown.

The undertaker must give to National Grid Electricity Transmission Plc not less than 14 days’ notice in writing of its intention to commence construction of any National Grid Connection Works and notice in writing of its completion not later than 7 days after the date on which it is completed and National Grid Electricity Transmission Plc will be entitled by its officer to watch and inspect the construction of such works.