# The Fenwick Solar Farm Order 2026, Paragraph 98: Arbitration


Save for differences or disputes arising under paragraphs 90(2), 90(4), 91(1) and 92 any difference or dispute arising between the undertaker and National Grid Electricity Transmission under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 43 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2026/151/schedule/14/paragraph/98 (the official version)
Page: https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-14/paragraph-98
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.