# The Fenwick Solar Farm Order 2026, Paragraph 10: Surface and foul water drainage


(1) No part of the authorised development may commence until details of the surface water drainage strategy and (if any) foul water drainage system (including means of pollution control) for that part have been submitted to and approved by the relevant planning authority in consultation with the Environment Agency.
(2) The approved drainage strategy must be substantially in accordance with the framework drainage strategy.
(3) Any strategy approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction and operation of the authorised development.
(4) For the purposes of sub-paragraph (1), “commence” includes any site preparation works.

---
Source: https://www.legislation.gov.uk/uksi/2026/151/schedule/2/paragraph/10 (the official version)