  "url": "https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-2/paragraph-12",
  "json_url": "https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-2/paragraph-12.json",
  "legislation": "uksi/2026/151",
  "legislation_title": "The Fenwick Solar Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/fenwick-solar-farm-order-2026",
  "path": "schedule/2/paragraph/12",
  "kind": "paragraph",
  "number": "12",
  "heading": "Construction environmental management plan",
  "text": "(1) No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority. Such approval to be in consultation with the relevant highway authority and the Environment Agency.\n(2) The construction environmental management plan must be substantially in accordance with the framework construction environmental management plan and must be implemented as approved.\n(3) The plan submitted and approved pursuant to sub-paragraph (1) must include a site waste management plan that must be substantially in accordance with the framework site waste management plan and must be implemented as approved.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/151/schedule/2/paragraph/12",
    "retrieved_at": "2026-10-28T21:05:56.633745+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}