Paragraph 9 Fencing and other means of enclosure

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until details of all proposed temporary fences, walls or other means of enclosure, including those set out in the construction environmental management plan, for that part have been submitted to and approved by the relevant planning authority.

(2)

No part of the authorised development may commence until details of all permanent fences, walls or other means of enclosure, including those set out in the construction environmental management plan, for that part have been submitted to and approved by the relevant planning authority.

(3)

For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary works.

(4)

Any construction site must remain securely fenced in accordance with the approved details under requirement 12(1) at all times during construction of the authorised development.

(5)

Any temporary fencing must be removed on completion of the part of construction of the authorised development for which it was used.