  "url": "https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-6/part-4",
  "json_url": "https://openlegislation.uk/fenwick-solar-farm-order-2026/schedule-6/part-4.json",
  "legislation": "uksi/2026/151",
  "legislation_title": "The Fenwick Solar Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/fenwick-solar-farm-order-2026",
  "path": "schedule/6/part/4",
  "kind": "part",
  "number": "4",
  "heading": "TEMPORARY MANAGEMENT OF PUBLIC RIGHTS OF WAY",
  "text": "(1)\nArea\n(2)\nPublic right of way\n(3)\nMeasure\nCity of Doncaster Council\nFenwick-12 between PRoW 03/01 and PRoW 04/01\nPublic Right of Way between PRoW 03/01 and PRoW 04/01 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-10 between PRoW 03/02 and PRoW 04/05\nPublic Right of Way between PRoW 03/02 and PRoW 04/05 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-14 between PRoW 03/03 and PRoW 06/02\nPublic Right of Way between PRoW 03/03 and PRoW 06/02 as shown on Sheets 3 and 6 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-15 between PRoW 03/04 and PRoW 04/07\nPublic Right of Way between PRoW 03/04 and PRoW 04/07 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-16 between 03/05 and 03/10\nPublic Right of Way between PRoW 03/05 and PRoW 03/10 as shown on Sheet 3 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-11 between PRoW 03/07 and PRoW 03/08\nPublic Right of Way between PRoW 03/07 and PRoW 03/08 as shown on Sheet 3 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-11 between PRoW 03/09 and PRoW 05/01\nPublic Right of Way between PRoW 03/09 and PRoW 05/01 as shown on Sheets 3 and 5 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-12 between PRoW 04/02 and PRoW 04/03\nPublic Right of Way between PRoW 04/02 and PRoW 04/03 as shown on Sheet 4 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-13 between PRoW 04/06 and PRoW 06/03\nPublic Right of Way between PRoW 04/06 and PRoW 06/03 as shown on Sheets 4 and 6 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nFenwick-11 between PRoW 05/02 and PRoW 05/03\nPublic Right of Way between PRoW 05/02 and PRoW 05/03 as shown on Sheet 5 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nMoss-5 between PRoW 05/03 and PRoW 05/04\nPublic Right of Way between PRoW 05/03 and PRoW 05/04 as shown on Sheet 5 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nMoss-6 between PRoW 06/01 and PRoW 06/02\nPublic Right of Way between PRoW 06/01 and PRoW 06/02 as shown on Sheet 6 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nMoss-20 between PRoW 07/01 and PRoW 07/02\nPublic Right of Way between PRoW 07/01 and PRoW 07/02 as shown on Sheet 7 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nThorpe in Balne-6 between PRoW 08/01 and PRoW 08/02\nPublic Right of Way between PRoW 08/01 and PRoW 08/02 as shown on Sheet 8 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nThorpe in Balne-7 between PRoW 08/03 and PRoW 08/04\nPublic Right of Way between PRoW 08/03 and PRoW 08/04 as shown on Sheet 8 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nThorpe in Balne-8 between PRoW 09/01 and PRoW 09/02\nPublic Right of Way between PRoW 09/01 and PRoW 09/02 as shown on Sheet 9 of the streets, access and rights of way plans to be managed during construction of the authorised development\nCity of Doncaster Council\nThorpe in Balne-13 between PRoW 09/03 and PRoW 09/04\nPublic Right of Way between PRoW 09/03 and PRoW 09/04 as shown on Sheet 9 of the streets, access and rights of way plans to be managed during construction of the authorised development",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/151/schedule/6/part/4",
    "retrieved_at": "2026-10-28T21:05:56.633745+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}