# The Ferrybridge Multifuel 2 Power Station Order 2015, Paragraph 13: Surface and foul water drainage

Extent: E+W+S

(1) Each part of the authorised development must not commence until written details of the surface and foul water drainage systems (including means of pollution control, in accordance with the CEMP) for that part have been submitted to and, after consultation with the Environment Agency, approved by the planning authority.
(2) The details submitted and approved must be in accordance with the principles and strategy set out in Appendix 12A to the environmental statement.
(3) The surface and foul water drainage systems must be constructed in accordance with the relevant approved details.
(4) The authorised development must not be commissioned until the surface and foul water drainage systems have been constructed.

---
Source: https://www.legislation.gov.uk/uksi/2015/1832/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/ferrybridge-multifuel-2-power-station-order-2015/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.